Ambode completed 54 roads, abandoned 74 in 2018 – Report

Published

on

Tracka, a subsidiary of BudgIT, which tracks the implementation of government projects in their community, on Friday released its report on 2018 road construction by the Akinwunmi Ambode-led government in Lagos State.

A statement by Damen Ilevbaoje, Head, Tracka, said while the breakdown of the total cost (N18,545,657,940.00), remains unknown to the public, the Lagos State Government last year flagged off the construction of 181 roads spread across the 20 Local Governments and 37 Local Council Development Areas (LCDAs).


Lagos State Commissioner for Works and Infrastructure, Engr. Ade Akinsanya said in a press statement February 2018 that “the roads will be done in phases.

“The first phase consists of 57 roads cutting across the 20 Local Governments and 37 Local Council Development Areas.”

Tracka said it deployed two Field Officers to monitor, very closely, the progress of the projects vis-à-vis budget implementation and quality delivery.

“Given the population and rising number of industries in Lagos, the government’s effort to repair roads, reduce mishaps and ease traffic is duly commendable”, it noted.

“However, it is imperative to note that the financial breakdown of the projects remains secret.

“The only information in the public space is the gross amount allocated for the roads and the part payment by the state government. As such, the quest for transparency and accountability is fiercely strangled by the government.

READ ALSO  Lady seen teaching Igbo to students in Chinese University (Video below)

“Out of 175 roads tracked by our team, only 54 are completed; 38 are ongoing while 8 bear unspecified locations, all at the time of our last visit in February 2019. Tracka confidently reports that a higher number of the roads (74) are yet to be constructed.

“More surprisingly, a number of roads that have been completed in the 114 Roads in 2016 are recaptured in the new project (e.g. Community Road in Alimosho LGA).

“Aside from abandoned roads, some projects have been left off worse than they actually were before the intervention, making life harder for commuters and members of the community. A typical case is Ayilara street in Surulere LGA.

“Finally, we observed some glitches in the construction of certain routes ranging from poor quality to contractors’ disappearance from sites to lack of proper implementation. In specific terms, the use of substandard materials like Asphalt and Bitumen, which often lead to the short lifespan of roads, is also recorded.”